ANALISIS PENJADWALAN PROYEK REPETITIF DENGAN METODE KESEIMBANGAN GARIS (LINE OF BALANCE) (Studi Kasus : Proyek Gedung Multifungsi Samanea)

Goldhand Christopher, Shenantiasya (2022) ANALISIS PENJADWALAN PROYEK REPETITIF DENGAN METODE KESEIMBANGAN GARIS (LINE OF BALANCE) (Studi Kasus : Proyek Gedung Multifungsi Samanea). S1 thesis, UNIVERSITAS SULTAN AGENG TIRTAYASA.

[img] Text
Shenantiasya Goldhand Christopher_3336180043_Fulltext.pdf

Download (30MB)
[img] Text
Shenantiasya Goldhand Christopher_3336180043_CP.pdf

Download (23kB)
[img] Text
Shenantiasya Goldhand Christopher_3336180043_01.pdf

Download (3MB)
[img] Text
Shenantiasya Goldhand Christopher_3336180043_02.pdf

Download (2MB)
[img] Text
Shenantiasya Goldhand Christopher_3336180043_03.pdf

Download (2MB)
[img] Text
Shenantiasya Goldhand Christopher_3336180043_04.pdf

Download (2MB)
[img] Text
Shenantiasya Goldhand Christopher_3336180043_05.pdf

Download (3MB)
[img] Text
Shenantiasya Goldhand Christopher_3336180043_06.pdf

Download (2MB)
[img] Text
Shenantiasya Goldhand Christopher_3336180043_Ref.pdf

Download (2MB)
[img] Text
Shenantiasya Goldhand Christopher_3336180043_Lamp.pdf

Download (28MB)

Abstract

Scheduling and planning are critical to the success of the project. This study discusses the effective rescheduling of buildings with case studies on Multifunction Building Projects that have repetitive work. The Multifunction Building Project consists of a Mall building which has 3 floors and a Multi Purpose Building (MPB) which has 23 floors. The project has an overall duration of 672 days. The method used is the Line of Balance method in the form of a vertical line that describes the work unit and a horizontal axis that describes time. Quantitative research is presented in the form of numerical information. The data in the form of a master schedule and worker data are processed so as to make an effective Line of Balance diagram with each diagram line not intersecting each other. The results showed that the total effective scheduling using the Line of Balance method for the duration of the Mall building and Multi Purpose Building was 514 days and 338 days. There is a difference in duration in the Mall building 158 days later than the existing schedule and in the Multi Purpose Building 127 days faster than the existing schedule. It can be concluded that the Line of Balance method is effective when used in buildings that have many building units/floors.

Item Type: Thesis (S1)
Contributors:
ContributionContributorsNIP/NIM
Thesis advisorMaddeppungeng, Andi195910171988031003
Thesis advisorBudiman, Arief197105272005011001
Additional Information: Penjadwalan dan perencanaan sangat menentukan keberhasilan proyek. Penelitian ini membahas tentang penjadwalan ulang yang efektif pada bangunan yang berstudi kasus pada Proyek Gedung Multifungsi yang memiliki pekerjaan bersifat repetitif. Proyek Gedung Multifungsi terdiri dari bangunan Mall yang memiliki 3 lantai dan Multi Purpose Building (MPB) yang memiliki 23 lantai. Proyek ini memiliki durasi secara keseluruhan 672 hari. Metode yang digunakan yaitu metode Line of Balance yang berupa garis vertikal yang menggambarkan unit pekerjaan dan sumbu horizontal yang menggambarkan waktu. Penelitian kuantitatif disajikan dalam bentuk informasi angka. Data yang berupa master schedule, dan data pekerja diolah sehingga menjadikan sebuah diagram Line of Balance yang efektif dengan tiap garis diagram tidak saling berpotongan. Hasil penelitian menunjukan total penjadwalan efektif dengan menggunakan Metode Line of Balance durasi pada bangunan Mall dan Multi Purpose Building didapatkan 514 hari dan 338 hari. Terdapat selisih durasi pada bangunan Mall 158 hari lebih lambat daripada existing schedule dan pada bangunan Multi Purpose Building 127 hari lebih cepat dibanding existing schedule. Dapat disimpulkan bahwa metode Line of Balance efektif bila digunakan pada bangunan yang memiliki unit/ lantai bangunan yang banyak.
Subjects: T Technology > TA Engineering (General). Civil engineering (General)
T Technology > TH Building construction
Divisions: 03-Fakultas Teknik
03-Fakultas Teknik > 22201-Jurusan Teknik Sipil
Depositing User: Mr Shenantiasya Goldhand Christopher
Date Deposited: 07 Dec 2022 10:48
Last Modified: 07 Dec 2022 10:48
URI: http://eprints.untirta.ac.id/id/eprint/18025